Quick answer: A grinding-line RFQ is a specification, not a wish list. Six fields decide the quote, plus a template on material, PSD basis, capacity, utilities and acceptance.
Key takeaways for a grinding-line RFQ
- An RFQ is a specification, not a wish list. The supplier can only quote what you define. Every vague line — "fine grinding", "high capacity" — comes back as an assumption you did not choose.
- Six fields do most of the work. Material and feed form, target particle size with its test basis, capacity in your units, viscosity or thermal limits, utilities and hazard classification, and the acceptance protocol. Get these right and the rest is detail.
- Always state the PSD test basis. "D90 of 5 µm" means nothing without the method — laser diffraction under ultrasonicated wet dispersion behaves differently from a grind gauge. Specify ISO 13320 and the dispersion condition.
- Give both average and peak capacity. Sizing to a peak that happens twice a week oversizes the machine; sizing to an average understates it. State both and the duty cycle.
- Declare the utilities you actually have. Cooling water, power, compressed air and floor space cap what can be supplied. A mill that needs 4 m³/h of cooling water cannot run on a site that supplies 1 m³/h.
- Define acceptance before you order. Agree the test method, the sampling point and the pass criteria in the RFQ, so "acceptance" is a measurement rather than an opinion.
Why most grinding-line RFQs come back with the wrong quote
A request for quotation is the single document that decides whether the equipment you receive can make your product. Yet most RFQs in this industry are a paragraph of prose: a product name, a rough capacity and a request for "best price". The supplier then fills the gaps with their own assumptions, and the quotation that returns is accurate for a machine you did not ask for.
The problem is not the supplier's diligence. It is that grinding performance is a function of several variables that interact — material hardness, feed size, target fineness, viscosity, media, residence time and cooling. Leave any of them out and the machine can be technically correct and commercially wrong at the same time.
This guide turns the RFQ into a structured specification. It follows a simple principle used in professional procurement: for every field, state what the buyer supplies and what the supplier must respond with. That symmetry makes it obvious when a quotation has skipped a requirement. The structure below is drawn from published equipment-selection practice and POLYC's own configuration data; the numbers are a framework, and each line should be confirmed on your material with a test.
There is also a commercial reason to do this properly. When three suppliers quote against the same written specification, their prices become comparable and their technical differences become visible. When they each quote against a loose paragraph, the cheapest number usually reflects the lightest machine — and the difference only appears when the line fails to hold fineness on your hardest product. The RFQ is therefore not paperwork; it is the tool that makes a price comparison meaningful.
If you already know which mill family you need, the chamber sizing guide explains how to translate capacity into a working volume before you write the RFQ.
The six fields that decide the quote
Before the template, understand what each field is protecting you against. Most failed equipment purchases trace back to one of these six being underspecified.
1. Material and feed form. Name the product, its chemistry and its incoming state — dry powder, press cake, slurry or paste. State the feed size (F80 or F97) and the solids content. A mill sized for a slurry cannot be judged against a paste, and a press cake needs a different upstream stage than a dry powder.
2. Target particle size and its test basis. State the target D50 and D90, and state how it will be measured. Specify ISO 13320 laser diffraction with the dispersion condition, or a grind gauge to ISO 1524 / ASTM D1210 if that is your plant standard. Two labs can report different D90 values on the same sample if the dispersion method differs, so the method is part of the requirement (the particle size guide explains why).
3. Capacity in your units. Give the average and the peak, and say whether the figure is finished product or feed. Add the number of passes or the recirculation strategy if the product needs more than one. A flow rate without a pass count is only half a specification.
4. Viscosity or thermal limits. Provide the viscosity at operating temperature, not at room temperature. For heat-sensitive products add the maximum allowable temperature rise. This single field often decides whether a bead mill, a basket mill or a three roll mill is the right answer.
5. Utilities and hazard classification. List the power supply, cooling-water flow and temperature available, compressed air if needed, and the floor space. Declare the solvent or dust hazard classification so the supplier can quote the correct electrical and sealing specification — this is a compliance line, not a detail.
6. Acceptance protocol. Define how the machine will be accepted: the test material, the sampling point, the measurement method and the pass criteria. A supplier who knows the acceptance test in advance quotes to it; one who does not will negotiate it later.
The RFQ template — buyer supplies, supplier responds
The table below is the working core of the RFQ. Copy it into your document and fill the left column. The right column tells you what a complete response should contain, so you can see at a glance which lines came back empty.
| RFQ field | What you (buyer) supply | What the supplier must respond with |
|---|---|---|
| Material | Product name, chemistry, hazard notes, representative sample quantity | Material compatibility, restrictions, recommended contact materials |
| Feed form and size | Dry powder / press cake / slurry / paste; F80 or F97; solids % | Accepted feed range and any required pre-treatment |
| Target fineness | Target D50 / D90 and the test method (ISO 13320 wet, or grind gauge) | Achievable fineness with the proposed configuration, and the test basis |
| Capacity | Average and peak throughput, units, passes or recirculation | Rated and proven capacity, with margin and the basis of the figure |
| Viscosity / thermal | Viscosity at operating temperature; maximum allowable temperature rise | Viscosity rating and cooling capacity of the proposed machine |
| Utilities | Power supply, cooling water flow and temperature, air, floor space | Utility demand of the proposed machine versus what you can supply |
| Hazard / compliance | Solvent or dust zone classification, site requirements | Electrical, sealing and guarding specification that meets it |
| Acceptance | Test material, sampling point, method, pass criteria | Agreed test protocol and documented result |
| Lifecycle | Shifts, maintenance capability, changeover frequency | Service tasks, spares, consumables, training, warranty terms |
Two rows are routinely left blank by buyers and cost the most later: utilities and acceptance. A mill that meets the fineness target but needs more cooling water than the site supplies is not a working installation. A machine that passes an undefined acceptance test is not really accepted.
Specifying particle size correctly — the field most often got wrong
Particle size is where RFQs most often fail, because the number is quoted without its method. The same sample can read differently depending on whether it was measured by laser diffraction under ultrasonication, by a grind gauge, or by sieving.
State the requirement in a way that cannot be interpreted loosely: the target value, the statistic (D50, D90 or D97), the instrument method and standard (for example ISO 13320), and the dispersion condition. If your plant judges fineness by grind gauge, say so and give the gauge reading — but recognise that a gauge reading and a laser D90 are not interchangeable, and the supplier needs to know which one governs acceptance.
| Fineness statement | What it leaves open | Better way to write it |
|---|---|---|
| "Grind to 5 micron" | Which statistic, which method, which dispersion | "D90 ≤ 5 µm by ISO 13320 laser diffraction, ultrasonicated wet dispersion" |
| "Fine dispersion" | Everything | "Hegman gauge ≥ 7 to ISO 1524 on the finished batch" |
| "Same as our current product" | No reference sample or data | Supply a reference sample plus its measured D50/D90 and the method used |
| "Nano" | Ambiguous below 1 µm | "D50 ≤ 200 nm by ISO 13320, with the dispersion protocol stated" |
The dispersion stage upstream of the mill affects the achievable fineness as much as the mill does, so note in the RFQ whether the feed is pre-dispersed or not. A mill asked to both wet out and refine will be sized differently from one receiving a stable premix.
Capacity, passes and the duty cycle
Capacity is not one number. A grinding line has an average demand, a peak demand and a duty cycle, and the machine must be sized for the correct one. State all three in the RFQ and say which the quotation should be based on.
Add the number of passes or the recirculation strategy. A product that needs three passes through the mill has an effective capacity one third of a single-pass figure at the same flow. If the quotation says "2,000 L/h" and your product needs three passes, the real output is roughly 670 L/h of finished product — a gap that surfaces only after installation unless it is written down in advance.
The throughput troubleshooting guide explains the other half of this: if the pre-dispersion is weak, the mill appears to lack capacity even when it is running at its rated flow. Stating the upstream stage in the RFQ lets the supplier size the mill for the feed it will actually receive, not an idealised one.
Utilities and hazard — the lines that cap the whole design
Utilities are the most common reason a technically suitable machine cannot be installed. Cooling water is the usual culprit: demand rises steeply with chamber volume and energy density, and a site that supplies a modest flow cannot run a large high-energy mill regardless of what the quotation promises.
List what you have, not what you wish you had. Power supply and available current, cooling-water flow and inlet temperature, compressed air if the design needs it, and the floor space and headroom available. Then require the supplier to state the machine's demand against each. The table below is a utility declaration you can paste into the RFQ; the right-hand column is the discipline that prevents a late surprise.
| Utility | Declare on the site | Require the supplier to state | Why it can stop the installation |
|---|---|---|---|
| Electrical supply | Voltage, phases, frequency, available current | Connected load and full-load current at the proposed duty | An under-rated supply cannot start a large mill under a full media charge |
| Cooling water | Flow available, inlet temperature, quality | Required flow at rated duty and the allowable rise | Heat accumulation changes viscosity and colour; undersupply is the classic failure |
| Compressed air | Pressure and flow available, if any | Consumption and pressure requirement of the design | Some sealing and discharge systems depend on it |
| Floor space and headroom | Footprint, height, access for maintenance | Machine envelope and service clearances | A mill that fits on the drawing may not fit the room or the door |
| Ambient conditions | Room temperature range, ventilation | Permissible ambient range | Heat rejection into a closed room raises the working temperature further |
The chamber volume guide gives published cooling-water figures for different mill sizes as a reference point — small units at roughly 500 L/h rising to several thousand litres per hour on the largest chambers. Use those figures to sanity-check whether a proposed machine is within your site's capability before you compare prices.
Hazard classification is a compliance matter. If the product contains solvent, the electrical and sealing specification changes, and a quotation built for a water-based line will not be compliant. Declare the zone or classification in the RFQ so the supplier quotes the correct build. Where explosion protection is required, state it explicitly rather than assuming it is included.
Acceptance — define it before you order
The last field is the one that protects the whole purchase. Acceptance should be a measurement, not a negotiation after delivery. Write into the RFQ: the material to be used for the test, the sampling point, the measurement method and the pass criteria.
A practical acceptance protocol includes the fineness result on the agreed method, the throughput achieved at that fineness, the temperature rise across the batch, and the time to change over between products if that matters to your operation. Agreeing these in advance means the factory acceptance test has a pass or fail outcome rather than a discussion. The turnkey project process page describes how acceptance is handled on a complete line.
For a three roll mill application, the particle size guide sets out the pass sequence and how to check it, which makes a good basis for the acceptance criteria.
Common RFQ mistakes and how to avoid them
Asking for a price before a specification. A price without a specification cannot be compared between suppliers, because each is pricing a different machine. Write the specification first; the price then becomes comparable.
Copying a competitor's datasheet. A datasheet describes a machine, not your requirement. Use it for reference if you like, but state your own material, target and constraints.
Leaving the test basis implicit. "D90 of 5 µm" invites three different measurement methods and three different results. State the standard and the dispersion condition.
Omitting the duty cycle. A peak-only or average-only capacity figure misleads the sizing. Give both and say which governs.
Forgetting the upstream and downstream stages. A mill is one part of a line. State what feeds it and what it feeds, so the supplier can size it for the real process.
No acceptance clause. Without it, "acceptance" becomes whatever both parties can agree after the fact. Define it in the RFQ.
A one-page RFQ checklist
- Material — product, chemistry, hazard, sample quantity.
- Feed — form, F80/F97, solids content, pre-dispersed or not.
- Fineness — D50/D90 plus the standard and dispersion condition, or the grind gauge reading.
- Capacity — average, peak, duty cycle, passes or recirculation.
- Viscosity and temperature — at operating condition, with the allowable rise.
- Utilities — power, cooling water flow and temperature, air, space.
- Hazard — zone classification and any explosion-protection requirement.
- Acceptance — material, sampling point, method, pass criteria.
- Lifecycle — maintenance capability, changeover frequency, spares expectation.
- Scope boundary — what feeds the mill and what it feeds, so nothing is assumed.
Turning the RFQ into a trial
A good RFQ ends with a request for a material test, not just a quotation. Ask the supplier to run your sample and report the fineness result on the agreed method, the throughput achieved and the temperature rise. That converts the quotation from a promise into evidence.
POLYC offers a material test and a configuration review so the quotation rests on measured behaviour with your product. Request a test slot through the contact page, and see the pigment solutions overview for how grinding fits into the wider line. For product options, start from the pin type bead mill, the static disc bead mill and the PTM triple roller mill ranges.
What the supplier does with your six fields
Each field in a well-written RFQ removes a guess. Material composition sets contact parts and wear expectations. Particle size with a test method sets the mill type and the number of passes. Capacity with passes sets chamber volume. Rheology sets the drive and cooling duty. Utilities and hazard set the electrical and safety package. Acceptance sets what counts as success.
Because the fields are linked, a change in one propagates. Raising the solids content changes viscosity, which changes the cooling duty, which can change the chamber choice. Give the supplier the production range, not a single ideal point, so the quote holds when the plant moves.
Expect a good supplier to come back with questions where a field is missing. If a quote arrives without a single clarification, it is probably a template rather than an engineered response.
Frequently asked questions
What should a grinding line RFQ include?
At minimum: the material and its feed form, the target particle size with the test method, capacity as average and peak with the number of passes, viscosity and allowable temperature rise, the utilities you can supply, the hazard classification, and the acceptance protocol. Add the upstream and downstream stages so the supplier can size the mill for the real process. Each field should say what you supply and what the supplier must respond with.
How do I specify particle size so suppliers quote the same thing?
State the statistic, the method and the dispersion condition together. For example: D90 not exceeding 5 microns by ISO 13320 laser diffraction under ultrasonicated wet dispersion. If your plant uses a grind gauge, state the gauge reading under ISO 1524 or ASTM D1210 and say that it governs acceptance. Without the method, the same number can mean different results from different labs.
Should the RFQ state average or peak capacity?
Both, plus the duty cycle and which figure the quotation should be based on. Sizing to a rare peak oversizes the machine and leaves it underused; sizing to the average understates the requirement and risks shortfall. Also state the number of passes, because a multi-pass process has an effective output well below the single-pass flow rate.
What utilities do I need to declare in the RFQ?
Power supply and available current, cooling-water flow rate and inlet temperature, compressed air if required, and the floor space and headroom available. Cooling water is the most common constraint because demand rises steeply with mill size and energy density. Declaring what you actually have lets the supplier rule out configurations you cannot run before quoting them.
Do I need to mention explosion protection in the RFQ?
Yes, if the product contains solvent or generates combustible dust. The zone or hazard classification changes the electrical and sealing specification, and a quotation built for a water-based line will not be compliant. State the classification and any site requirement explicitly, so the supplier quotes the correct build rather than assuming a standard one.
How should acceptance be defined in the RFQ?
Define it as a measurement: the test material, the sampling point, the measurement method and the pass criteria. Include the fineness result on the agreed method, the throughput at that fineness, the temperature rise and, if relevant, the changeover time. Agreeing this before ordering turns the factory acceptance test into a pass-or-fail outcome rather than a negotiation after delivery.
Relevant POLYC MACHINE equipment
Related technical guides
Standards referenced
Method references used by process engineers when specifying and verifying the operations described in this guide.
- ISO 13320:2020 - Particle size analysis - Laser diffraction methods
- ISO 1524:2020 - Paints, varnishes and printing inks - Determination of fineness of grind
- ASTM D1210-05(2022) - Standard Test Method for Fineness of Dispersion of Pigment-Vehicle Systems by Hegman-Type Gage