PROJECT DELIVERY
Turnkey Project Process: From URS to Final Acceptance
The stages, deliverables and responsibilities for a wet grinding or mixing plant project, from the first specification review to final acceptance.
The stages, deliverables and responsibilities for a wet grinding or mixing plant project, from the first specification review to final acceptance.
A turnkey project moves from URS review to process design, plant layout, itemised and total quotation, manufacturing with factory acceptance testing, shipping, on-site installation and commissioning, operator training and final acceptance. Each stage has a defined deliverable and a named owner on both sides.
What Turnkey Covers — and What It Does Not
A turnkey line means POLYC takes responsibility for process design, equipment supply, factory testing, shipping, installation supervision, commissioning and training up to final acceptance. It does not mean we build the factory building or supply raw materials.
Civil works, utilities brought to the battery limit, local permits, raw materials and packaging consumables normally stay with the customer. Stating this boundary early prevents scope disputes late in a project.
Stage 1: URS and Process Data Review
Where a customer supplies a URS or technical specification attachment, we review it clause by clause and return a compliance list, deviations and open questions. Where no URS exists, the RFQ checklist provides the minimum data set to start process design.
The output of this stage is an agreed process basis: products, capacities, viscosity and fineness targets, utilities and site constraints.
Stage 2: Process Design and Equipment List
The process basis is converted into a flow: powder induction and pre-dispersion, grinding or fine dispersion, let-down, filtration and filling, with holding vessels and transfer equipment between stages. The equipment list then follows, with model references and quantities.
Capacity is checked against batch size and cycle time, so the stated annual output is arithmetically achievable rather than nominal. See the paint and coating production line and ink production line for representative configurations.
Stage 3: Plant Layout and Drawings
Equipment positions, material flow, operator access, maintenance clearance, ceiling height and lifting provisions are laid out on a drawing. Hazardous-area zoning is marked where solvent-based products are handled. The existing paint line layout guide explains the main decisions in more detail.
Layout deliverables are issued for customer review before manufacture, because changes are inexpensive on paper and expensive after fabrication.
Stage 4: Quotation — Itemised and Total
Two figures are provided separately: an itemised equipment quotation, and a turnkey total including the services in scope. This mirrors how many customers compare supplier offers. Commercial terms, packing, destination and Incoterm are stated with the quotation; see the RFQ checklist for the inputs that feed it.
No prices are published on this website.
Stage 5: Manufacturing and Factory Acceptance
Equipment is fabricated, assembled and checked at the factory. A factory acceptance test can be witnessed on site or supported by test documentation. A factory visit can be arranged for customers who want to see the equipment and the assembly process before shipment.
Stage 6: Shipping, Installation and Commissioning
Equipment is packed for export and shipped to the agreed Incoterm point. On site, installation supervision covers positioning, alignment, utility connections and safety checks. Commissioning then runs water or solvent trials and trial batches, resolving issues before handover.
Stage 7: Training, Acceptance and After-Sales
Operators are trained on start-up, routine operation, cleaning, changeover and basic troubleshooting. Final acceptance is recorded against the agreed criteria. Warranty scope, recommended spare parts and after-sales support are documented at handover.
Comparable delivered projects are listed under case studies, for example the 15,000 t/y latex paint line and the resin production line.
Deliverables Matrix and FAQ
| Stage | POLYC deliverable | Customer input / cooperation |
|---|---|---|
| 1 URS review | Compliance list, deviations, agreed process basis | URS or process data, formula constraints |
| 2 Process design | Flow, equipment list, capacity calculation | Confirm products and duty cycle |
| 3 Layout | Layout drawing, zoning, access clearances | Building dimensions, utility points |
| 4 Quotation | Itemised quotation and turnkey total | Commercial terms, destination port |
| 5 Manufacture & FAT | Test records, FAT attendance if required | Witness attendance or document review |
| 6 Shipping & commissioning | Packing, supervision, trial batches | Site readiness, utilities, local labour |
| 7 Training & acceptance | Training, acceptance record, warranty documents | Operators, acceptance sign-off |
Questions
What does a turnkey scope include?
Process design, equipment supply, FAT, shipping, installation supervision, commissioning, training and acceptance — but not civil works or raw materials.
Do you provide civil construction?
No. Building structure and utilities to the battery limit are normally in the customer scope.
How is a URS handled?
It is reviewed clause by clause, with a compliance list, deviations and open questions returned before design.
Can we attend FAT or visit the factory?
Yes, a factory acceptance test and factory visit can be arranged before shipment.
Who supplies utilities and raw materials?
The customer normally brings utilities to the battery limit and supplies raw materials and packaging consumables.
What happens after final acceptance?
Warranty, recommended spare parts and after-sales support continue as documented at handover.