SC lines are sized by batch rhythm, not by annual tonnage. Enter the target output, batch size and cycle time, and the calculator returns batches per day, mill volume and the number of mills needed.

Calculate

5
Daily output—
Batches per day—
Required batch capacity—
Mills required—
Milling flow per mill—
Note—

 

Batches per day = daily output × 1,000 / batch size. Batch hours required = batches × cycle time. Mills = required hours ÷ available hours. Milling flow per mill ≈ batch size ÷ passes ÷ cycle time.

Batch cycle time is the number to challenge

An SC batch cycle includes premix, milling, let-down, thickening and QC hold. Of these, milling usually dominates, but let-down and thickening can add hours if the thickener needs hydration time. Ask what the cycle time includes before using it here.

Reducing cycle time by 20% is often cheaper than buying a second mill, and it usually comes from premix quality and dispersant choice rather than from milling harder.

Why parallel mills beat one big mill for SC

SC batches are limited by heat and by the need to keep the particle size distribution tight. Two mills in parallel each doing a full batch give better temperature control and let you take one offline for maintenance without stopping the line. A single oversized mill has no redundancy and concentrates the heat load.

Frequently asked questions

Does batch size affect the mill count?

Yes, strongly. Doubling the batch halves the number of batches, but doubles the milling time per batch, so the product of the two — total milling hours — stays roughly constant.

What cycle time should I use for a new product?

Use your pilot data where possible. For a new SC, 4–6 hours is a realistic planning range including let-down and thickening.

Should I plan for 100% utilisation?

No. Plan at 75–85% to allow cleaning, maintenance and changeover. A line planned at 100% will miss its output every month.

How does recirculation change the calculation?

Recirculation increases the effective passes without a separate mill, so the milling flow per mill rises while the residence time per pass falls.