Paint Production Line

Paint Line ROI Calculator

Payback is arithmetic, not opinion, but it only works with your numbers. Enter the investment, the additional output, your margin and the change in running cost, and see the payback period and three-year return.

Calculate

10
Annual gross benefit—
Simple payback—
Three-year ROI—
Approximate NPV at 8%—
Note—

 

Annual benefit = additional output × (margin − change in running cost). Simple payback (months) = investment ÷ annual benefit × 12. Three-year ROI = (3 × benefit − investment) ÷ investment. NPV discounts each year's benefit at 8%.

The assumption that breaks most business cases

Additional output is usually the weakest input. A line that can make 1,500 t more per year only creates value if that tonnage can be sold at the assumed margin. Model the case at 50% of the assumed extra output as well: if the payback becomes unacceptable, the project depends on market assumptions rather than on the equipment.

Margin per tonne is the other sensitive input. A 10% change in margin moves payback by roughly the same proportion, which is why finance teams ask for margin evidence rather than equipment quotations.

What the model leaves out

Working capital, installation downtime, training, spare parts inventory and tax treatment are excluded. Installation downtime alone can cost one to three months of output on a line replacement, which is material for a 18-month payback case.

Frequently asked questions

Should I use simple payback or NPV?

Both. Simple payback answers cash timing; NPV answers whether the project creates value over the asset life. Decisions usually need both.

Why 8% for the discount rate?

It is a common hurdle rate for industrial equipment in a stable currency. Use your own cost of capital if it differs.

How do I treat an efficiency improvement rather than extra output?

Enter zero extra output and a negative change in running cost. The model handles it: the benefit comes from cost reduction.

Does the calculator include maintenance?

Only through the running cost input. Add maintenance separately if it is material for your asset.