Energy per tonne = installed power × average load × 6,000 hours / annual output × price. Labour per tonne = shift cost × shifts × days / output. Total = (energy + media + labour) ÷ (1 − yield loss).
Paint Production Line
Running cost per tonne is what decides whether a line makes money at your selling price. Enter your own rates and the estimator returns the cost per tonne split by driver, so you can see which lever moves the total.
Energy per tonne = installed power × average load × 6,000 hours / annual output × price. Labour per tonne = shift cost × shifts × days / output. Total = (energy + media + labour) ÷ (1 − yield loss).
Labour per tonne falls roughly in proportion to output, so a 20,000 t/yr line carries half the labour cost of a 10,000 t/yr line on the same staffing. Energy per tonne also falls with output if the equipment runs near design capacity instead of at part load.
This is why two plants with identical equipment can have very different costs: one runs at design flow, the other runs at 40% and pays the same power for half the tonnage.
Paint lines lose product to cleaning, changeover, filtration residues and off-spec batches. A 2% loss on a 10,000 t/yr line is 200 tonnes; at a $400 margin that is $80,000 per year, which is often larger than the annual energy bill. Measure it before optimising anything else.
It is a common annual operating assumption for two-shift production with downtime. Adjust the inputs if your schedule is different.
Add it to the running cost if it is material. For most paint lines, maintenance is 3–5% of installed equipment value per year.
Enter each line's power, media and labour separately. The comparison is only fair at the same annual output.
No. Raw material cost is excluded because it depends on formulation rather than on equipment.