Three Roll Mill

Cooling Water Calculator

Three roll mills put most of their motor power into the paste as heat. If the cooling water cannot remove it, the gap closes, viscosity drops and dispersion quality drifts. This calculator returns the heat load and the water flow required at a chosen temperature rise.

Calculate

8
Heat to remove—
Water flow required—
Outlet temperature—
Note—

 

Heat load = motor power × load factor × 0.85 (the share of shaft power that ends up in the product). Water flow = 60 × heat / (4.186 × ΔT) in litres per minute.

Why roller cooling is a production issue, not a comfort issue

As rollers heat up they expand, and the gap you set cold is not the gap you run hot. On a manual mill the operator compensates by tightening, which raises pressure and wear. On a hydraulic mill the gap holds, but the paste viscosity drops and the film thins, so output falls and fineness changes.

Cooling water also protects the product: pigments that are temperature sensitive can shift shade, and some pastes gel or skin on hot rollers. Sizing the flow properly is cheaper than sorting out a batch that drifted off shade.

Open loop or closed loop

Once-through water is simple and cheap to install but wasteful, and in warm climates the inlet temperature already limits the achievable ΔT. A closed loop with a chiller holds a stable inlet temperature, which makes the gap repeatable batch after batch. Above roughly 60 L/min, the operating cost of once-through water usually exceeds the cost of a small chiller.

Frequently asked questions

Is 0.85 the right share of motor power going into the product?

It is a reasonable default for a three roll mill at production gaps. At very fine films and high speeds, more of the power goes into shear and heat, so use 0.9.

Can I use a glycol mixture?

Yes, but its specific heat is lower, so you need about 10% more flow for the same ΔT, and the viscosity at low temperature affects pump selection.

What if my mill has no cooling on the rollers?

Then output and fineness are limited by heat build-up. Retrofitting internal roller cooling is usually possible but should be confirmed with the manufacturer before relying on it.

Does the apron need cooling too?

The apron and end plates benefit from cooling on large mills, but the rollers carry most of the heat load.

Get a Quote →WhatsApp
Chat on WhatsApp